Approval of statement of intent to comply. Upon receipt of the applicant's statement of intent to comply with the established conditions, the Planning Board shall, within 120 days, forward to the Town Board its recommendation to conditionally approve or disapprove the development subject to such conditions and to completion of the required environmental review. During this 120-day period the Planning Board shall review details regarding compliance with §
270-32, Planned Development Area (PDA), and §
270-27, Site plan review, and, within the first 30 days of the review period, a public comment period will be established to consider §
270-27, Site plan review, and §
270-32, Planned Development Area (PDA), issues. A PDA site plan review shall require, in addition to the other requirements of this chapter:
(1)
A statement as to the effect of the proposed PDA on the objectives of the Comprehensive Plan and the character of the neighborhood.
(2)
A statement identifying potential significant adverse impacts that should be included in an environmental review.
(3)
A statement of the conditions and covenants that shall be followed by the applicant in developing the proposed planned development.
(4)
The applicant's statement of intent to comply with the required conditions.
(5)
A recommendation on the amount and type of performance guarantee which the developer should provide.